Bulletin # 27 Update – 14/04/2023
The decisions of An Bord Pleanála dated 6 December 2021 granting approval for the N6 Galway City Ring Road have been quashed, …
The decisions of An Bord Pleanála dated 6 December 2021 granting approval for the N6 Galway City Ring Road have been quashed, …
The N6 Galway City Ring Road has been approved (with conditions and modifications) by An Bord Pleanála. Link to An Bord Pleanála …
An Bord Pleanála have made arrangements for the resumed Oral Hearing for the N6 Galway City Ring Road project. The arrangements are as follows: …
The current design for the N6 Galway City Ring Road, including the proposed development boundary, can be found at the following link: …
Please note the following notice is on display on An Bord Pleanála website “26/03/2020 – Important Update: N6 Galway City Ring Road Oral …
An Bord Pleanála have decided to hold an oral hearing for the N6 Galway City Ring Road project. The arrangements for the …
As requested by An Bord Pleanála, the further information response notice which was advertised on the 30th September 2019 has now been …
The response to the Request for Further Information (RFI) received from An Bord Pleanála (ABP) was submitted Friday 30 August 2019. ABP …
The Application for the N6 Galway City Ring Road (GCRR) was lodged with An Bord Pleanála (ABP) in October 2018. Following that, …
All of the submissions/objections in relation to the N6 Galway City Ring Road (GCRR) Scheme have now been received by Galway County …
The Environmental Impact Assessment Report and Natura Impact Statement for the N6 Galway City Ring Road (GCRR) have been submitted to An …
The Environmental Impact Assessment Report and Natura Impact Statement for the N6 Galway City Ring Road (GCRR) have been submitted to An …
The planning application for the N6 Galway City Ring Road (GCRR) has been finalised and will be submitted to An Bord Pleanála …
The current design for the N6 Galway City Ring Road, including the proposed development boundary, can be found at the following links: …
The final meeting with An Bord Pleanála, as part of the pre-application consultation process, took place in the last month. The planning …
A final meeting with An Bord Pleanála to close out the consultation process with them is expected within the coming weeks. The …
The planning application documents for the N6 Galway City Ring Road (GCRR) are currently being finalised for submission to An Bord Pleanála, …
The current design for the N6 Galway City Ring Road, including the proposed development boundary, can be found at the following link: …
All land required for the construction and operation of the N6 Galway City Ring Road (GCRR) is to be compulsory acquired through …
Following further assessment undertaken as part of the design process, which included a road safety audit, peer review and traffic analysis, the …
Following further assessment undertaken as part of the design process, which included a road safety audit, peer review and traffic analysis, the …
Due to the high level of engagement received by the N6 Galway City Ring Road project office, the design phase has been …
There is no deadline for submissions based on the current design that is currently on public display in Galway City and County …
The Galway Transport Strategy (GTS), which aims to deliver an overall transport solution for Galway and environs, is being advanced by Galway …
Individual landowner letters and drawings have been posted to all directly impacted landowners to provide an update on the project, the current …
Please find the following link to drawings showing the latest design from the Galway Racecouse to the existing N6 Galway to Dublin …
Please find the following link to drawings showing the latest design from the River Corrib to the N84 Headford Road: http://www.n6galwaycity.ie/wp-content/uploads/2016/06/GCOB-SK-D-679-680_River_Corrib-to-N84_Current_Design2-Sheets.pdf We …
The published Route Selection Report is now available on the project website at the following link: http://www.n6galwaycity.ie/phase-2/route-selection-report/.
Figure 1.1 Green2 – Blue2 Switch Plan Layout Figure 3.2.1 Green2- Blue2 Switch with Ecology Constraints Habitats (Sheet 1 of 2) Figure 3.2.2 …
Volume 3A – Appendices Part 1 Volume 3B – Appendices Part 2 Volume 3C – Appendices Part 3 Volume 3D – Appendices …