Bulletin # 14 Update of Project Timeline – 12/12/2017
The planning application documents for the N6 Galway City Ring Road (GCRR) are currently being finalised for submission to An Bord Pleanála, …
The planning application documents for the N6 Galway City Ring Road (GCRR) are currently being finalised for submission to An Bord Pleanála, …
The current design for the N6 Galway City Ring Road, including the proposed development boundary, can be found at the following link: …
All land required for the construction and operation of the N6 Galway City Ring Road (GCRR) is to be compulsory acquired through …
Following further assessment undertaken as part of the design process, which included a road safety audit, peer review and traffic analysis, the …
Following further assessment undertaken as part of the design process, which included a road safety audit, peer review and traffic analysis, the …
Due to the high level of engagement received by the N6 Galway City Ring Road project office, the design phase has been …
There is no deadline for submissions based on the current design that is currently on public display in Galway City and County …
Please find the following link to drawings showing the latest design from the Galway Racecouse to the existing N6 Galway to Dublin …
Please find the following link to drawings showing the latest design from the River Corrib to the N84 Headford Road: http://www.n6galwaycity.ie/wp-content/uploads/2016/06/GCOB-SK-D-679-680_River_Corrib-to-N84_Current_Design2-Sheets.pdf We …
The published Route Selection Report is now available on the project website at the following link: http://www.n6galwaycity.ie/phase-2/route-selection-report/.
In the current project programme the planning application documents (Environmental Impact Statement and Compulsory Purchase Order) will be ready for publication by …
Alternative Design Options and subsequent chosen Designs for the N6 Galway City Transport Project are listed below:
Following feedback received from landowner meetings, submissions received and further assessment the design option to be progressed for the Ballindooley, Castlegar and …
Please find the following link to a drawing showing the latest design from the R336 Coast Road to the N59 Moycullen Road: …
Following feedback received from landowner meetings and submissions received, the design option to be progressed from Ballymoneen Road to N59 Moycullen Road …
Following feedback received from landowner meetings, submissions received and further assessment the design option to be progressed from Na Foraí Maola to …
Two alternative design options have been developed for the Ballindooley, Castlegar and Ballybrit areas following feedback received during the public consultation sessions, …
Three alternative design options have been developed in the Cappagh area following feedback received during the public consultation sessions, landowner meetings and …
Volume 3B – Appendices Part 2 – Table of Contents A.5.1 Lough Corrib Route Options A.5.2 Coastal Route Options Report A.5.3 On-line …
Volume 3A – Appendices Part 1 – Table of Contents A.2.1 Phase 1 Preliminary Appraisal A.3.1 Traffic Modelling Report A.3.1 Traffic Modelling …
Three alternative design options have been developed in the Trusky West to Aille area following feedback received during the public consultation sessions, …
Six alternative design options have been developed in the Na Foraí Maola and Trusky West area following feedback received during the public …
The deadline for submissions in relation to Public Consultation No.3 for the N6 Galway City Transport Project is the 12th of June …
The public consultation material for the N6 Galway City Transport Project is on display at the N6 Project Office from 9.30am to …
N6 Galway City Transport Project Route Selection Public Consultation No.2 Galway County Council is co-ordinating the development of a transportation solution for …
The project is currently at Phase 4. A copy of the Environmental Impact Assessment Report and Natura Impact Statement were submitted to …
Arup completed the first phase of the project in 2014. The objective of this phase is to identify the need for a …
Technical Map showing Engineering, GAS , ESB, Cultural Heritage Constraints Technical Map showing Landscape & Agronomy Constraints Technical Map showing Socio Economic, …